Factory Shutdown Calendar

Not confirming your supplier's actual dates

Not confirming your supplier's actual dates: the generic calendar vs the specific one.

The mistake

Planning on regional estimates and official calendars, never asking the supplier. Every factory's window differs — sometimes by two weeks within one city. The generic calendar is a prior; the supplier's answer is the fact.

The two questions

"What are your exact last production day and first day back?" and "Where do your workers go home to?" The first gives the window; the second predicts its reliability.

When to ask

November, then again in January. Plans drift as the date approaches and order books fill — two confirmations catch the drift.

The rule

Estimates for planning, confirmations for commitment. Never commit money to an unconfirmed date.

Know the date, plan the order. The factory shutdown calendar shows CNY dates to 2035, estimated shutdown windows, and your last practical order date.