Factory Shutdown Calendar

Freight cost impact of CNY (estimates)

The freight cost impact of CNY: how much the peak surcharge adds, in numbers.

The estimate

WindowRate vs baseline
Normal100%
Pre-CNY peak (last 2–3 weeks)120–150%
During CNY~100% but thin capacity
Post-CNY (first weeks)110–130% as backlog drains

The worked example

A 100 kg air shipment at a $6/kg baseline costs $600. Shipping in the pre-CNY peak at 130% costs $780 — $180 more. Same goods, same route, three weeks' timing difference.

The decision frame

The $180 premium buys certainty of pre-holiday delivery. Compare it against the alternative: waiting three weeks for backlog drain. For most products, the maths favours shipping early — the premium is cheaper than a stockout.

The note

Ranges are estimates for planning; actual surcharges come from forwarders' quotes, which should be requested in November.

Know the date, plan the order. The factory shutdown calendar shows CNY dates to 2035, estimated shutdown windows, and your last practical order date.