Factory Shutdown Calendar

Inventory planning around a 3-week shutdown

Inventory planning around a 3-week shutdown: the coverage calculation with numbers.

The calculation

Coverage weeks = shutdown (3) + restart ramp (2) + transit (4) = 9 weeks. Multiply by weekly sales: 200 units/week → 1,800 units needed on hand or in transit before the window closes.

The worked example

ComponentValue
Weekly sales200 units
Coverage needed9 weeks
Buffer target1,800 units
Plus safety stock (20%)+360
Total2,160 units

The cash view

2,160 units at $5 landed is $10,800 of inventory — the hidden CNY tax on the business. Calculate it in November so the cash is planned, not discovered.

The refinement

Replace the generic 3-week shutdown with your supplier's confirmed dates and the generic 4-week transit with your route's actual time. The method is constant; the inputs are personal.

Know the date, plan the order. The factory shutdown calendar shows CNY dates to 2035, estimated shutdown windows, and your last practical order date.