Inventory planning around a 3-week shutdown
Inventory planning around a 3-week shutdown: the coverage calculation with numbers.
The calculation
Coverage weeks = shutdown (3) + restart ramp (2) + transit (4) = 9 weeks. Multiply by weekly sales: 200 units/week → 1,800 units needed on hand or in transit before the window closes.
The worked example
| Component | Value |
|---|---|
| Weekly sales | 200 units |
| Coverage needed | 9 weeks |
| Buffer target | 1,800 units |
| Plus safety stock (20%) | +360 |
| Total | 2,160 units |
The cash view
2,160 units at $5 landed is $10,800 of inventory — the hidden CNY tax on the business. Calculate it in November so the cash is planned, not discovered.
The refinement
Replace the generic 3-week shutdown with your supplier's confirmed dates and the generic 4-week transit with your route's actual time. The method is constant; the inputs are personal.
Know the date, plan the order. The factory shutdown calendar shows CNY dates to 2035, estimated shutdown windows, and your last practical order date.