How to add a CNY buffer to lead times
How to add a CNY buffer to lead times: the simple rule and its exceptions.
The rule
Any lead time that crosses the CNY window gets +3 weeks (shutdown) plus +2 weeks (ramp). Crossing means the order's production or transit period overlaps late January through late February in the relevant year.
The exceptions
| Case | Buffer |
|---|---|
| Order fully produced and shipped before the window | +0 |
| Order crosses the window | +3 to +5 weeks |
| Order placed inside the window | +5 weeks and rising |
The discipline
Apply the buffer at quoting time, not after the delay happens. A customer quoted ten weeks who receives goods in ten weeks is happy; one quoted five who waits ten is gone.
The note
The buffer is an estimate; the supplier's confirmed dates convert it into fact. Buffer first, confirm second.