Factory Shutdown Calendar

How to add a CNY buffer to lead times

How to add a CNY buffer to lead times: the simple rule and its exceptions.

The rule

Any lead time that crosses the CNY window gets +3 weeks (shutdown) plus +2 weeks (ramp). Crossing means the order's production or transit period overlaps late January through late February in the relevant year.

The exceptions

CaseBuffer
Order fully produced and shipped before the window+0
Order crosses the window+3 to +5 weeks
Order placed inside the window+5 weeks and rising

The discipline

Apply the buffer at quoting time, not after the delay happens. A customer quoted ten weeks who receives goods in ten weeks is happy; one quoted five who waits ten is gone.

The note

The buffer is an estimate; the supplier's confirmed dates convert it into fact. Buffer first, confirm second.