Factory Shutdown Calendar

Lead time example with CNY in the middle

A lead time example with CNY in the middle: how a 5-week lead becomes 10.

The example

Normal lead time: 5 weeks. Order placed January 10, CNY on February 6. Weeks 1–2: production starts. Weeks 3–5: shutdown swallows three weeks. Restart: ramp adds two more. Delivery: late March — about ten weeks after the order.

The arithmetic

ComponentWeeks
Normal lead time5
Shutdown added+3
Restart ramp added+2
Effective lead time~10

What this teaches

A CNY-crossing order doubles its lead time. The lead time is not a product property — it is a calendar property. The same order placed November 1 sails through in the normal five weeks.

The rule

Any lead-time quote that crosses the window gets the shutdown added — automatically, before quoting the customer, not after.

Know the date, plan the order. The factory shutdown calendar shows CNY dates to 2035, estimated shutdown windows, and your last practical order date.