Lead time example with CNY in the middle
A lead time example with CNY in the middle: how a 5-week lead becomes 10.
The example
Normal lead time: 5 weeks. Order placed January 10, CNY on February 6. Weeks 1–2: production starts. Weeks 3–5: shutdown swallows three weeks. Restart: ramp adds two more. Delivery: late March — about ten weeks after the order.
The arithmetic
| Component | Weeks |
|---|---|
| Normal lead time | 5 |
| Shutdown added | +3 |
| Restart ramp added | +2 |
| Effective lead time | ~10 |
What this teaches
A CNY-crossing order doubles its lead time. The lead time is not a product property — it is a calendar property. The same order placed November 1 sails through in the normal five weeks.
The rule
Any lead-time quote that crosses the window gets the shutdown added — automatically, before quoting the customer, not after.
Know the date, plan the order. The factory shutdown calendar shows CNY dates to 2035, estimated shutdown windows, and your last practical order date.