How to order before Chinese New Year

How to order before Chinese New Year: the timeline that gets your order produced before the shutdown.

The timeline

WhenAction
8 weeks beforeConfirm specs, pricing and supplier capacity
6 weeks beforePlace the order in writing
4 weeks beforeConfirm production slot and QC schedule
2 weeks beforeTrack production, arrange freight
1 week beforeEverything shipped or explicitly delayed

Why eight weeks

The pre-CNY period compresses: production slots fill, freight sells out, and the supplier's attention fragments. Starting early is not caution — it is the only way to be inside the normal rhythm rather than chasing it.

The written-order rule

Everything in writing: specs, quantities, delivery date, penalty terms. Verbal promises made in December are the most common source of February disputes.

The pairing

Use the shutdown calendar to back out your deadline from the CNY date. The calendar gives the date; this checklist gives the sequence.

Know the date, plan the order. The factory shutdown calendar shows CNY dates to 2035, estimated shutdown windows, and your last practical order date.