Ignoring the port backlog
Ignoring the port backlog: the post-CNY queue that delays even on-time cargo.
The mistake
Assuming that cargo shipped on time arrives on time. After CNY, ports drain a three-week pile-up: containers stacked, customs thin, trucking scarce. Your on-time shipment can still lose two weeks in the queue.
The backlog mechanics
Pre-holiday rush fills the yard → holiday pause stops the drain → post-holiday restart processes the queue. Everything entering that queue pays with time, regardless of when it was shipped.
The mitigation
- Ship early enough to clear the port before the slowdown
- Or ship after the backlog drains (mid-March onwards)
- Track the shipment through the port, not just to it
The rule
The CNY delay budget has two parts: the factory window and the port queue. Budget for both or discover the second one the hard way.