Factory Shutdown Calendar

How the shutdown affects production

How the CNY shutdown affects production: the fade-out, the stop, and the slow restart.

The three phases

PhaseTimingOutput
Fade-out1–2 weeks before CNYDeclining, then minimal
Full stopCNY ± a weekZero
Restart ramp2–3 weeks after50% → 70% → 100%

The fade-out

Output drops before the official holiday as workers leave early to travel. An order promised for "before the holiday" may be produced at 50% staffing — which is how late-January orders quietly slip.

The restart ramp

The first week back runs at partial capacity: some workers are still travelling, others have not returned at all. Suppliers quote "reopened on February X" — the honest question is "at what capacity".

The planning implication

Add the fade-out and the ramp to any lead-time calculation that crosses the window. The shutdown is not a three-week hole; it is a five- to six-week distortion.

Know the date, plan the order. The factory shutdown calendar shows CNY dates to 2035, estimated shutdown windows, and your last practical order date.