How the shutdown affects production
How the CNY shutdown affects production: the fade-out, the stop, and the slow restart.
The three phases
| Phase | Timing | Output |
|---|---|---|
| Fade-out | 1–2 weeks before CNY | Declining, then minimal |
| Full stop | CNY ± a week | Zero |
| Restart ramp | 2–3 weeks after | 50% → 70% → 100% |
The fade-out
Output drops before the official holiday as workers leave early to travel. An order promised for "before the holiday" may be produced at 50% staffing — which is how late-January orders quietly slip.
The restart ramp
The first week back runs at partial capacity: some workers are still travelling, others have not returned at all. Suppliers quote "reopened on February X" — the honest question is "at what capacity".
The planning implication
Add the fade-out and the ramp to any lead-time calculation that crosses the window. The shutdown is not a three-week hole; it is a five- to six-week distortion.
Know the date, plan the order. The factory shutdown calendar shows CNY dates to 2035, estimated shutdown windows, and your last practical order date.