The formula

Reorder point = (lead time + CNY buffer) × weekly demand + safety stock. The CNY buffer is the piece most formulas omit — and it is the piece that matters most in Q4 and Q1.

The worked example

ComponentValue
Normal lead time5 weeks
CNY buffer+4 weeks
Effective lead time9 weeks
Weekly demand150 units
Base reorder point1,350 units
Safety stock (15%)+200 units
Final reorder point1,550 units

The seasonal adjustment

The reorder point should rise through Q4 as the window approaches, then drop back in spring. A fixed reorder point is a February stockout waiting to happen.

The note

The buffer value comes from the shutdown calendar's estimates, refined by your supplier's confirmed dates.